How to change the due finish date for a work order
- Go to the Permit module.
- Enter the Work Orders tab.
- Locate the work order using the filters on the left-hand side. Ensure you press Search to apply the filters.
- Press the Pencil icon within the Action column on the right of the page:

- Within the Due Finish Date option, press the date box.
- Choose the preferred finish date.
- Press the Update button:

Related Articles
What are the Due Start and Finish Dates within a work order?
The Due Start Date and Due Finish Date options within a work order define the duration of the work. The Due Start Date indicates when the work is scheduled to begin. The work order cannot be submitted before this date. The Due Finish Date indicates ...
How to change the due start date for a work order
Go to the Permit module. Enter the Work Orders tab. Locate the work order using the filters on the left-hand side. Ensure you press Search to apply the filters. Press the Pencil icon within the Action column on the right of the page: Within the Due ...
How to create a work order as an administrator
Go to the Permit module. Enter the Work Orders section. Press the Create New Work Order button: Enter the work order's details within the popup. Press Create once the mandatory fields have been populated: Please note: The following fields are ...
Why can't I locate a work order in the admin portal?
If you’re having trouble locating a work order in the Administrator Portal, there are a few common reasons this may occur. The work order date range is outside your search criteria When searching for a work order, ensure the Date Range is set to All ...
How to create a work order as a contractor administrator
Sign into your MyRapid account at https://my.rapidglobal.com/account/sign-in Press the Contracting company administrator / B2B tile within the sign-in options: Press the relevant Client Portal tile: Dropdown the Company tab on the left-hand side. ...